15.Asset Retirement and Reclamation Obligations

 

Asset retirement obligations ("ARO") for the Lost Creek Project are equal to the present value of all estimated future costs required to remediate any environmental disturbances that exist as of the end of the period, using discount rates ranging from 0.3% to 3.3%.  Included in this liability are the costs of closure, reclamation, demolition and stabilization of the mines, processing plants, infrastructure, aquifer restoration, waste dumps and ongoing post-closure environmental monitoring and maintenance costs. At December 31, 2014, the total undiscounted amount of the future cash needs was estimated to be $12.1 million. The schedule of payments required to settle the ARO liability extends through 2033.

 

Asset retirement obligations for the Pathfinder properties are equal to the present value of all estimated future costs required to remediate any environmental disturbances that exist as of the end of the period, using a discount rate of 3.0%.  Included in this liability are the costs of closure, reclamation, demolition and stabilization of the mines, processing plants, infrastructure, aquifer restoration, waste dumps and ongoing post-closure environmental monitoring and maintenance costs. At December 31, 2014, the total undiscounted amount of the future cash needs was estimated to be $12.7 million. The schedule of payments required to settle the ARO liability extends through 2033.

 

The undiscounted future cash needs are based on information provided to the State of Wyoming in conjunction with annual reclamation bonding renewals.  Increases in the estimated future cash needs are normally based on increased disturbances projected for the upcoming year.  In 2014, there was no increase in the estimated liability on the Lost Creek Project as the anticipated disturbance was less than what had been projected in the previous year.  In addition, the Company submitted their initial report to the state since acquiring the Pathfinder properties.  The total estimated liability was significantly greater than what had been reflected on the Pathfinder financial statements at of the date of the acquisition in 2013.  As a result, the estimated liability was revised in 2014 to reflect the estimates calculated by Company personnel.

 

The restricted cash as discussed in note 7 is related to surety bonds and letters of credit which provide security to the related governmental agencies on these obligations.

 

 

 

 

 

 

 

Year ended

 

Year ended

 

December 31, 2014

 

December 31, 2013

 

 

 

 

 

$

 

$

Beginning of year

17,279 

 

957 

Liabilities incurred

 -

 

10,639 

Assumed in Pathfinder Mines Corporation purchase

 -

 

5,656 

Change in estimated liability

5,669 

 

 -

Accretion expense

497 

 

27 

 

 

 

 

End of period

23,445 

 

17,279